Location: KIRKUK/YRAK
Contract Date: 2/2/22
Completion Date: 6/15/23
Duration: 499 days
Project Type: Factory
State: Completed
Customer: BC GRUPO
Main Contractor: BCM ULUS.MAD.INŞ.SAN VE TIC.A.S.
Scope of Work: 800 tons/day, 24,000 tons/month

Project Description: The BC STEEL FACTORY project is a steel production plant located in Kirkuk, Iraq. This project started on February 2, 2022 and was completed on June 15, 2023, taking a total of 499 days.

The project, ordered by BC GROUP and carried out by BCM ULUS.MAD.İNŞ.SAN VE TİC.A.Ş., includes the construction of a modern production facility with a steel production capacity of 800 tons per day and 24,000 tons per month. This project aimed to strengthen the industrial infrastructure in Kirkuk and meet the steel needs in the region.

BC STEEL FACTORY is located as one of the most important steel production facilities in the region with its high production capacity and modern technological infrastructure. The project aimed to increase efficiency in the steel production process and provide high quality products.

BCM ULUS.MAD.İNŞ.SAN VE TİC.A.Ş., by successfully completing the BC STEEL FACTORY project, made a significant contribution to the industrial sector in Kirkuk and served as an example for future industrial projects.